Construction season is underway in Unalaska, with five projects scheduled between now and late November.

"These projects total approximately $10 million," said Director of Public Works Tom Cohenour.

More than half of that budget is going toward the continued expansion of the Unalaska Marine Center, where two aging docks are being replaced.

Summer Construction Season Starts In Unalaska

Jul 7, 2017
Berett Wilber/KUCB

It’s summer construction season in Unalaska, and drivers should expect road closures and delays around the island.

Director of Public Works Tom Cohenour said Captains Bay Road will experience the longest delays.

The road will be narrowed to one lane in August, so the city can trench and install 7,000 feet of new electrical wiring. Road crews will be there to ensure drivers don't wait for long.

“We have it as part of the contract that delays cannot be a longer than eight minutes,” said Coenhour. “That’ll allow traffic to keep flowing as much as possible.”